Pipe Lift - Ovolifts - Corrosion Under Pipe Supports (CUPS) - Touchpoint Corrosion - Pipeline Integrity - Asset Integrity

Rope Access On 4" Glycol Line

  • Uni Jacks utilized at 2nd and 3rd level of pipe rack.

  • Eliminated the need for a crane or scaffold at 80 locations.

  • Significant cost savings improved safety and increased productivity.

Ovolifts - Pipe Rack - Pipe Lifts

Terminal Rack - Delaware, USA

  • 568 pipe touchpoints lifted and repaired in 7 weeks.

  • Installed new ware pads whilst terminal was active.

  • Crew of 5 technicians using 12 Multi Jacks.

14" Crude Oil Line

  • 183 pipe touchpoints lifted over 6 weeks.

  • 17 major findings (wall loss of >50% net wall thickness).

  • 10 minor findings (wall loss <50% net wall thickness).

Mega-Jack - Pipe Jack - Pipe Lift
Ovolifts - Touchpoint Corrosion

High Pressure Tank Farm

  • 1,200 pipe touchpoints serviced within 3 months.

  • Wall thickness readings taken at each touchpoint.

  • Touchpoints and I-beams sandblasted and re-coated.

  • Teflon ware pads installed at all touchpoints.

Rope Access on 16" Flare

  • Engineered Line Lifting Provides Safe Access for Direct NDE Assessment of Damage

  • Assessment of Touchpoint Corrosion damage at 24 locations along 16” Flare System​

  • Inspection, Rope Access, Innovative Lifting Technology

  • LinkedIn
  • YouTube

© 2020 Ovolifts, LLC. All Rights Reserved. All services, methods and tools of Ovolifts, LLC, whether offered by this company or via any other channel are protected by copyright as well as US and international patents and pending patent applications.