top of page
Pipe Rack Jack _ Touchpoint Access _ Ovolifts.png

PROJECTS

project icon.png

NGL Lines Water Crossing

  • Touchpoint corrosion on NGL lines over a water crossing.

  • Challenging access and diagonal supports limited traditional methods of lifting.

  • Custom engineered solution provided for client on 1 weeks notice.

  • Significant cost savings for customer.

CUPS.jpg
DSC01212_edited.jpg

Marine Terminal Shoe Replacement

  • Pipe movement and touchpoint corrosion required direct access inspection and repairs.

  • 119 touchpoints across lines ranging in size from 8" to 24"

  • Challenging access over water.

Liquid Hammer & Damaged Pipe Repair

  • Liquid hammer caused significant pipe movement at the expansion loop.

  • Damaged pipe shoes removed to install enclosures at two locations.

  • Flair line integrity restored, supported by engineering line lifting.

Liquid Hammer | Flair Line | Pipe Rack Jack | Enclosure | Fitness For Service | Pipe Integrity | Pipe Shoe Damage | Guides
Ovolifts | Marine Terminal | Pipe Rack Jack | Corrosion Under Pipe Supports | CUPS | Jetty | Pipe Rack

Terminal Rack - Delaware, USA

  • 568 pipe touchpoints lifted and repaired in 7 weeks.

  • Installed new ware pads whilst terminal was active.

  • Crew of 5 technicians using 12 Multi Jacks.

Rope Access On 4" Glycol Line

  • Uni Jacks utilized at 2nd and 3rd level of pipe rack.

  • Eliminated the need for a crane or scaffold at 80 locations.

  • Significant cost savings improved safety and increased productivity.

Rope Access | NDT | I-Rod Installation
On-Stream Line Lifting | Pipe Rack Jack | Crude Oil | Ground Level Pipe Jack | Supports

14" Crude Oil Line

  • 183 pipe touchpoints lifted over 6 weeks.

  • 17 major findings (wall loss of >50% net wall thickness).

  • 10 minor findings (wall loss <50% net wall thickness).

High Pressure Tank Farm

  • 1,200 pipe touchpoints serviced within 3 months.

  • Wall thickness readings taken at each touchpoint.

  • Touchpoints and I-beams sandblasted and re-coated.

  • Teflon ware pads installed at all touchpoints.

Ovolifts Mega-Jack | Corrosion Under Pipe Supports | Pipe Rack Jack | Engineered Line Lifting | Multiple Pipes
Rope Access | Pipe Jack | Flair Line | Wall Loss | NDT | Corrosion Under Pipe Supports

Rope Access on 16" Flare

  • Engineered Line Lifting Provides Safe Access for Direct NDE Assessment of Damage

  • Assessment of Touchpoint Corrosion damage at 24 locations along 16” Flare System​

  • Inspection, Rope Access, Innovative Lifting Technology

bottom of page