top of page
Pipe Rack Jack _ Touchpoint Access _ Ovolifts.png

PROJECTS

project icon.png

36" Flare Lines

  • Composite repairs and mechanical enclosures on adjacent 36" flare lines.

  • Significant line weights and piping geometry required comprehensive engineering calculations.

  • Simultaneous lifting at multiple location required to minimize pipe stress and reaction loads.
IMG_6462_edited.jpg
IMG_6974_edited.jpg

60" Slug Catcher

  • A combined 470,000 lbs of lifting force required.

  • Complete stress analysis and lift plan required to engineer the lift.

  • Scope included removing the saddles for refurbishment.

Saddle Replacement

  • Replacement of 80 saddles on NGL lines

  • Lines ranging in size from 20" to 36"

  • Lifting by crane was ruled out by the owner due to the uncontrolled nature of the resulting lift.

  • An engineered approach was required.
20230216_154719_edited.jpg
IMG_7792_edited.jpg

Multiple Lines On Round Supports

  • Pipe movement and touchpoint corrosion required direct access inspection and repairs.

  • 160 touchpoints across lines ranging in size from 8" to 16".

  • Lifting from 8" round or circular supports.

NGL Lines Water Crossing

  • Touchpoint corrosion on NGL lines over a water crossing.

  • Challenging access and diagonal supports limited traditional methods of lifting.

  • Custom engineered solution provided for client on 1 weeks notice.

  • Significant cost savings for customer.

CUPS.jpg
DSC01212_edited.jpg

Marine Terminal Shoe Replacement

  • Pipe movement and touchpoint corrosion required direct access inspection and repairs.

  • 119 touchpoints across lines ranging in size from 8" to 24"

  • Challenging access over water.

Liquid Hammer & Damaged Pipe Repair

  • Liquid hammer caused significant pipe movement at the expansion loop.

  • Damaged pipe shoes removed to install enclosures at two locations.

  • Flair line integrity restored, supported by engineering line lifting.

Liquid Hammer | Flair Line | Pipe Rack Jack | Enclosure | Fitness For Service | Pipe Integrity | Pipe Shoe Damage | Guides
Ovolifts | Marine Terminal | Pipe Rack Jack | Corrosion Under Pipe Supports | CUPS | Jetty | Pipe Rack

Terminal Rack - Delaware, USA

  • 568 pipe touchpoints lifted and repaired in 7 weeks.

  • Installed new ware pads whilst terminal was active.

  • Crew of 5 technicians using 12 Multi Jacks.

Rope Access On 4" Glycol Line

  • Uni Jacks utilized at 2nd and 3rd level of pipe rack.

  • Eliminated the need for a crane or scaffold at 80 locations.

  • Significant cost savings improved safety and increased productivity.

Rope Access | NDT | I-Rod Installation
On-Stream Line Lifting | Pipe Rack Jack | Crude Oil | Ground Level Pipe Jack | Supports

14" Crude Oil Line

  • 183 pipe touchpoints lifted over 6 weeks.

  • 17 major findings (wall loss of >50% net wall thickness).

  • 10 minor findings (wall loss <50% net wall thickness).

High Pressure Tank Farm

  • 1,200 pipe touchpoints serviced within 3 months.

  • Wall thickness readings taken at each touchpoint.

  • Touchpoints and I-beams sandblasted and re-coated.

  • Teflon ware pads installed at all touchpoints.

Ovolifts Mega-Jack | Corrosion Under Pipe Supports | Pipe Rack Jack | Engineered Line Lifting | Multiple Pipes
Rope Access | Pipe Jack | Flair Line | Wall Loss | NDT | Corrosion Under Pipe Supports

Rope Access on 16" Flare

  • Engineered Line Lifting Provides Safe Access for Direct NDE Assessment of Damage

  • Assessment of Touchpoint Corrosion damage at 24 locations along 16” Flare System​

  • Inspection, Rope Access, Innovative Lifting Technology

bottom of page