

PROJECTS

NGL Lines Water Crossing
-
Touchpoint corrosion on NGL lines over a water crossing.
-
Challenging access and diagonal supports limited traditional methods of lifting.
-
Custom engineered solution provided for client on 1 weeks notice.
-
Significant cost savings for customer.
Marine Terminal Shoe Replacement
-
Pipe movement and touchpoint corrosion required direct access inspection and repairs.
-
119 touchpoints across lines ranging in size from 8" to 24"
-
Challenging access over water.
Liquid Hammer & Damaged Pipe Repair
-
Liquid hammer caused significant pipe movement at the expansion loop.
-
Damaged pipe shoes removed to install enclosures at two locations.
-
Flair line integrity restored, supported by engineering line lifting.
Terminal Rack - Delaware, USA
-
568 pipe touchpoints lifted and repaired in 7 weeks.
-
Installed new ware pads whilst terminal was active.
-
Crew of 5 technicians using 12 Multi Jacks.
Rope Access On 4" Glycol Line
-
Uni Jacks utilized at 2nd and 3rd level of pipe rack.
-
Eliminated the need for a crane or scaffold at 80 locations.
-
Significant cost savings improved safety and increased productivity.
14" Crude Oil Line
-
183 pipe touchpoints lifted over 6 weeks.
-
17 major findings (wall loss of >50% net wall thickness).
-
10 minor findings (wall loss <50% net wall thickness).
High Pressure Tank Farm
-
1,200 pipe touchpoints serviced within 3 months.
-
Wall thickness readings taken at each touchpoint.
-
Touchpoints and I-beams sandblasted and re-coated.
-
Teflon ware pads installed at all touchpoints.
Rope Access on 16" Flare
-
Engineered Line Lifting Provides Safe Access for Direct NDE Assessment of Damage
-
Assessment of Touchpoint Corrosion damage at 24 locations along 16” Flare System
-
Inspection, Rope Access, Innovative Lifting Technology